IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO. 150 OF 2025 Nashik Infrastructure Developers Pvt Ltd

...Petitioner

Versus

Managing Director Maharashtra State Road Development Corporation Ltd

...Respondent

Mr. Anirudha A Garge, i/b Jitendra H Oak, for the Petitioner. Mr. Joshua D'Souza, a/w Saad Memon, i/b Bulwark Solicitor, for Respondent.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : JULY 24, 2025 ORDER :

1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Arbitral Tribunal, which expired on March 2, 2025.

2.

Having seen the record, it would be appropriate to extend the mandate upto January 31, 2026, bearing in mind the stage at which the arbitral proceedings are placed.

3.

In these circumstances, taking into account the stage at which the Arbitral proceedings are placed, this Petition is finally July 24, 2025 Ashwini Vallakati

912-ARP-150-2025.doc disposed of extending the mandate of the Arbitral Tribunal until January 31, 2026.

4.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] July 24, 2025 Ashwini Vallakati