Relcon Infraprojects Ltd v. Pune Cantonment Board
201-ARP-154-2025 copy.docx
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO. 154 OF 2025 Relcon Infraprojects Limited .. Petitioner Vs.
The Pune Cantonment Board .. Respondent Digitally signed by SHRADDHA KAMLESH TALEKAR Date:
2025.05.11 11:11:56 +0530 SHRADDHA KAMLESH TALEKAR Ms. Akanksha A. Mishra, for Petitioner.
Adv. Nelly Mehta i/b NMA Legal for the Respondent. CORAM : SOMASEKHAR SUNDARESAN, J.
Date : May 7, 2025 P. C.
1.
This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Arbitral Tribunal, which will expire on May 16, 2025.
2.
Having heard Learned Counsel for the parties, taking into account the stage at which the Arbitral proceedings are placed, this Petition is finally disposed of by extending the mandate of the Arbitral Tribunal for a period of two months from May 16, 2025, i.e. until July 16, 2025. 3.
All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website. [ SOMASEKHAR SUNDARESAN, J.] May 7, 2025 Shraddha