IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO. 201 OF 2025 WITH ARBITRATION PETITION NO. 164 OF 2025 Enkebee Infratech India Private Limited And Anr

...Petitioners

Versus

Thyssenkrupp Industries India Private Limited

...Respondent

Mr. S achchida Nand Pandey, for the Petitioners. Mr. Pranav Monam, a/w Vaishnavi Dalvi, i/b Kanqa & Co., for Respondent.

CORAM

: SOMASEKHAR SUNDARESAN, J.

DATE : AUGUST 13, 2025 ORDER :

1.

The Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Arbitral Tribunal, which expired on March 31, 2025.

2.

Today, when the matter is called out, Learned Counsel for the parties jointly request for an extension of the mandate until August 31, 2025, bearing in mind the stage at which the arbitral proceedings are placed.

Digitally signed by ASHWINI JANARDAN VALLAKATI Date:

2025.08.18 12:31:31 +0530 ASHWINI JANARDAN VALLAKATI August 13, 2025 Ashwini Vallakati

46-ARP-201-2025.doc 3.

In these circumstances, taking into account the stage at which the Arbitral proceedings are placed, this Petition is finally disposed of extending the mandate of the Arbitral Tribunal until August 31, 2025.

4.

Arbitration Petition No.164 of 2025 has been rendered infructuous by reason of extension of mandate granted above. Arbitration Petition No.164 of 2025 which is not on board, is, by consent of the parties taken on board and is also disposed of in the aforesaid terms.

5.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] August 13, 2025 Ashwini Vallakati