Solitaire Construction Pvt Ltd v. Ms Krishnae Infrastrcuture Pvt Ltd
14.ARP.273.2025.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
CIVIL APPELLATE JURISDICTION ARBITRATION PETITION NO.273 OF 2025 Solitaire Construction Pvt. Ltd.
....Petitioner
Versus
M/s Krishnae Infrastructure Pvt. Ltd. & Anr.
....Respondents Ms Vrushali Maindad, for Petitioner.
CORAM: SOMASEKHAR SUNDARESAN, J.
DATE : DECEMBER 22, 2025 ORDER :
1.
This is a Petition under Section 29A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Learned Arbitral Tribunal, which expired on January 8, 2025. 2.
Learned Counsel for Respondents entered appearance and accepts notice. Liberty to file Vakalatnama. 3.
Today, when the matter is called out, Learned Counsel for the parties jointly request for an extension of mandate by a period of six months, bearing in mind the stage at which the arbitral proceedings are placed.
4.
In these circumstances, taking into account the stage at which Digitally signed by AARTI GAJANAN PALKAR Date:
2025.12.23 17:05:20 +0530 the arbitral proceedings are placed, this Petition is finally disposed of AARTI GAJANAN PALKAR DECEMBER 22, 2025 Aarti Palkar
14.ARP.273.2025.doc extending the mandate of the Learned Arbitral Tribunal for a period of six months, rounding it up until June 30, 2026. 5.
All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.
[ SOMASEKHAR SUNDARESAN, J.] DECEMBER 22, 2025 Aarti Palkar