(1) 6 wp 971-2025

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH AT NAGPUR WRIT PETITION NO. 971 OF 2025 The Project Director, National Highway Authority of India, Project Implementation Unit Yavatmal, Chandrapur Vs.

Sandip S/o Premchand Chajed and another - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Office Notes, Office Memoranda of Coram, Court's or Judge's orders appearances, Court's orders of directions and Registrar's orders - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ---------------- - - - - - Shri A.A. Kathane, Advocate for petitioner Ms Mrunal Naik, AGP for respondent/State CORAM : SMT M.S. JAWALKAR, J.

DATE : 21.02.2025 Heard.

2.

Issue notice to the respondents, returnable on 04/03/2025.

3.

Learned Assistant Government Pleader waives notice for respondent No.2.

4.

It is submitted by learned Counsel for the petitioner that, in fact, there is recovery of Rs.45,728/-, due on 04/12/2024, from the respondent No.1, along with interest accrued thereon. However, to show bonafides they are ready to deposit 50% of amount claimed by respondent No.1 in execution proceedings.

(2) 6 wp 971-2025 5.

There shall be ad interim relief in terms of prayer Clause - (e), subject to payment of 50% (Rs.3,90,565/-) of amount in execution proceedings by 04/03/2025. 6.

In addition to usual mode of service, the petitioner is permitted to serve respondents by all modes available in law.

7.

Hamdast granted.

(SMT M.S. JAWALKAR, J.) Jayashree..