Bombay High CourtCAW/2484/2025allowed

Himanshu S/O Mangesh Dhote v. Dy. Commissioner And Vice-President, The S.T. Certificate Scrutiny Committee, Nagpur And ORS.

2025-10-17Hon'Ble Smt. Justice M. S. Jawalkar , Hon'Ble Shri Justice Raj D. Wakode2 pages

918caw2484.25 918caw2484.25

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH : NAGPUR NAGPUR BENCH : NAGPUR CIVIL APPLICATION (W) NO. 2484/2025 CIVIL APPLICATION (W) NO. 2484/2025 IN IN WRIT PETITION NO. 5036/2025 WRIT PETITION NO. 5036/2025 Himanshu Dhote Himanshu Dhote ..versus..

..versus..

Dy. Commissioner & Vice President, Scheduled Tribe Certificate Scrutiny Dy. Commissioner & Vice President, Scheduled Tribe Certificate Scrutiny Committee, Nagpur & others Committee, Nagpur & others ●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●● ●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●● Office Notes, Office Memoranda of Coram, Office Notes, Office Memoranda of Coram, Court's or Judge's orders Court's or Judge's orders appearances, Court's orders or directions appearances, Court's orders or directions and Registrar's orders and Registrar's orders ●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●● ●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●●● Shri K. Lilhare, Adv h/f Shri Ramteke, Adv for the Petitioner(s) Shri K. Lilhare, Adv h/f Shri Ramteke, Adv for the Petitioner(s) Shri J.Y. Ghurde, Shri J.Y. Ghurde, AGP AGP for the Respondent/State for the Respondent/State

CORAM

CORAM:-:- M.S. JAWALKAR & RAJ D. WAKODE, JJ.

M.S. JAWALKAR & RAJ D. WAKODE, JJ.

OCTOBER 17, OCTOBER 17, .

The present Application is filed by the Respondent - Caste Scrutiny Committee for extension of three months' time to decide the tribe claim of the Petitioner.

(2) It is contended that after direction to the Respondent - Scrutiny Committee, the Petitioner has submitted some validity certificates. The claim of the Petitioner is pending with the Police Vigilance Cell and the report is awaited. In view thereof, some more time is required, and hence, sought extension for further period of three months. (3) For the reasons stated in the Application, the Application is allowed. Further three months' time is extended to conclude the ..

..

A ..

..

A

918caw2484.25 918caw2484.25 enquiry and decide the tribe claim of the Petitioner. However, it is made clear that the Caste Scrutiny Committee shall make all endeavours to conclude the enquiry and decide the tribe claim of the Petitioner within the extended period. Interim protection granted to the Petitioner to continue till the decision of the Scrutiny Committee. (4) The Application stands disposed of.

(5) Learned AGP to communicate this order to the Respondent - Scrutiny Committee.

(RAJ D. WAKODE RAJ D. WAKODE, J.) , J.) (M.S. JAWALKAR, J.) (M.S. JAWALKAR, J.) ..

..