IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH AT NAGPUR CIVIL APPLICATION (CAF) NO.778 OF 2026 WITH CIVIL APPLICATION (CAF) NO.782 OF 2026 IN FIRST APPEAL (STAMP) NO.3958 OF 2025 V.I.D.C., THR. ITS EXECUTIVE ENGINEER PROJECT CONSTRUCTION DIVISION, AMRAVATI

VERSUS

RAMESH SHIORAMJI RANE AND OTHERS Office Notes, Office Memoranda of Coram, Appearances, Court's orders or directions and Registrar's orders Court's or Judge's orders Mr. U.A. Gosavi, Advocate for Applicant/Appellant. Ms. P.T. Joshi, AGP for Respondent Nos.4 & 5-State. CORAM : PRAFULLA S. KHUBALKAR, J.

DATED : 06th FEBRUARY 2026 1.

Heard learned Advocate for the applicant.

2.

Issue notice to the respondents, returnable after four weeks.

3.

Learned AGP waives service of notice on behalf of respondent Nos.4 and 5-State.

CIVIL APPLICATION (CAF) NO.782 OF 2026 4.

By this application filed under Order 41, Rule 5 of C.P.C., the appellant seeks stay to the Judgment and Award dated 08.11.2024, passed by the Reference Court at Nagpur. 5.

Issue notice to the respondents, returnable after four weeks.

2 53. CAF 778 of 2026.odt 6.

Learned AGP waives service of notice on behalf of respondent Nos.4 and 5-State.

7.

The appellant is permitted to serve the other respondents by private mode, in addition to regular mode of service and file affidavit of service in that regard by next date. 8.

Subject to the appellant depositing the entire amount of compensation along with interest, in this Court, within a period of one week from today, there shall be ad-interim stay to the impugned Judgment and Award, till next date.

(PRAFULLA S. KHUBALKAR, J.) asd