← Library
Bombay High CourtCAO/719/2025ca disposed off

Union Of India Through Chief Project Manager/ Chief Engineer (N), Central Railway, Nagpur v. M/S. Abhi Engineering Corporation Pvt Ltd, Mumbai, Thr. Authorized Signatory, Sanjay R. Vijaywargi

2025-07-21Hon'Ble Shri Justice Rohit Wasudeo Joshi1 pages

1 39-CAO 719.2025.odt

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

NAGPUR BENCH, NAGPUR CIVIL APPLICATION (O) NO. 719 OF 2025 IN M.C.A. (STAMP) NO. 15013 OF 2025 (REVIEW) IN M.C.A.(ARBN) NO. 407 OF 2024 (D) ( Chief Project Manager / Chief Engineer (N) Central Railway Mumbai vs. M/s.Abhi Engineering Corporation Pvt.Ltd. ) Office Notes, Office Memorandum of Coram, appearances, Court's orders of the directions, Court's or Judge's order and Registrar's orders.

Ms.Ishika Jaiswal, Advocate h/f Mr.S.A.Chaudhari, Advocate for appellant.

Mr. S.O.Tapdiya, Advocate for respondent.

CORAM : ABHAY J. MANTRI, J.

ATE : JULY 21, 2025 1) Learned counsel for the respondent seeks two weeks' time to file reply in the matter.

2) Time as prayed is granted.

3) List the matter on 18/08/2025.

(ABHAY J. MANTRI, J.) KOLHE Signed by: Mr. Ravikant Kolhe Designation: PA To Honourable Judge Date: 21/07/2025 15:12:56