Bombay High CourtPIL/10/2025disposed off

Shriniwas Gyandeorao Mundhe v. The Union Of India Through Its Secretary And Others

2025-03-17Hon'Ble Smt. Justice Vibha Kankanwadi , Hon'Ble Shri Justice Hiten S. Venegavkar2 pages

92-PIL-10-2025.odt

IN THE HIGH COURT OF JUDICATURE OF BOMBAY

BENCH AT AURANGABAD 92 PUBLIC INTEREST LITIGATION NO. 10 OF 2025 SHRINIWAS GYANDEORAO MUNDHE

VERSUS

THE UNION OF INDIA THROUGH ITS SECRETARY AND OTHERS ....

Mr. P. S. Paranjape, h/f Mr. P. N. Kalani, Advocate for the Petitioner Mr. R. R. Bangar, Advocate for Respondent Nos. 1 and 2 Mr. A. B. Girase, Government Pleader for Respondent Nos. 3 to 9 ....

CORAM : MANGESH S. PATIL & Y. G. KHOBRAGADE, JJ.

DATE : 17.03.2025 PER COURT :- The Petitioner is questioning the propriety of undertaking the work to construct a flyover/ over-bridge over the railway track, on the basis of a communication from respondent Nos. 1 and 2 (Railways) dated 25.07.2024 suggesting that in the light of possibility of project for a double-line being undertaken at about 2 to 3 kms., away from the existing track, the construction of road over-bridge may not be necessary for the time being.

(( 2 )) 92-PIL-10-2025 2.

Issue notice to the respondents for final disposal, returnable on 15.04.2025.

3.

Mr. Bangar, the learned advocate waives service of notice on behalf of respondent Nos. 1 and 2. Learned Government Pleader waives service of notice on behalf of respondent Nos. 3 to 9. They seek time.

4.

The tender process may go on, but the work order shall not be issued till the next date without permission of the Court. [ Y. G. KHOBRAGADE, J. ] [ MANGESH S. PATIL, J.] SMS