Central Railway Thr. The Deputy Chief Engineer (Construction) v. Ramavatar Rumanand Gadiya Deceased Thr. Lrs Jitendra Rumavatar Gadiya
903 Ia-676-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 676 OF 2025 IN FIRST APPEAL (St.) NO. 1400 OF 2025 Central Railway Through The Deputy Chief Engineer (Construction) Panvel Railway Station, District Raigad ...Applicant.
Versus
Ramavatar Rumanand Gadiya (Deceased) through LRs and Others
...Respondents.
------ Ms. Leena Patil for Appellant.
Mr. A. R. Patil, AGP for Respondent-State.
Mr. Saurabh Bhutala for Respondent.
------ Coram : Sharmila U. Deshmukh, J.
Date : January 17, 2025.
P. C. :
1.
Interim Application has been preferred for condonation of delay of 107 days caused in preferring the First Appeal. Appeal arises from the proceedings under the Land Acquisition Act, 1894 and considering the explanation, delay of 107 days is condoned. 2.
Interim Application stands disposed of.
[Sharmila U. Deshmukh, J.] Sairaj 1 of