← Library
Bombay High CourtIA/3169/2025disposed off

Suman Ankush Todkar v. The Executive Engineer

2025-03-05Hon'Ble Shri Justice Sandeep V. Marne1 pages

Kishor 904 IA 3169 of 2025.docx

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION INTERIM APPLICATION NO. 3169 OF 2025 IN CIVIL REVISION APPLICATION (L) NO. 761 OF 2020 WITH INTERIM APPLICATION (L) NO.10016 OF 2021 Suman Ankush Todkar ...APPLICANT V/S.

The Executive Engineer Sina Kolegaon Prlject Paranda & Ors.

...RESPONDENT ______________ Mr. Prashant D. Patil, for the Applicant.

_______________ CORAM : SANDEEP V. MARNE, J.

Dated : 5 March 2025.

P.C. :

1.

The Application is filed for restoration of the petition, which is dismissed due to non-removal of office objections. Considering the pleadings in the application so also the final order that the Court proposes to pass in the main Revision Application, petition is restored by condoning the delay.

2.

Interim Application is accordingly disposed of. SANDEEP V. MARNE, J.

Page No.

1 of 5 March 2025 KISHOR VISHNU KAMBLE by KISHOR VISHNU KAMBLE Date: 2025.03.07 15:03:12 +0530