Bombay High CourtIA/7426/2025disposed off

Executive Engineer Kadwa Right Canal Division, Nashik. v. Bhagwat Radhu Sapnar And ORS.

2025-04-21Hon'Ble Ms. Justice Gauri Godse2 pages

13-IA-7426-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION TALLE SHUBHAM ASHOKRAO INTERIM APPLICATION NO. 7426 OF 2025 TALLE SHUBHAM ASHOKRAO Date: 2025.04.22 18:34:36 +0530 IN FIRST APPEAL (ST) NO. 15139 OF 2023 Executive Engineer, Kadwa Right Canal Division, Nashik ...Applicant

Versus

Bhagwat Radhu Sapnar And Ors.

...Respondents

------ Adv. Chaitrali Deshmukh for the Applicant.

Mr. Mayur Sonavane AGP for the State.

------ Coram : Sharmila U. Deshmukh, J.

Date : April 21, 2025.

P. C. :

1.

Interim Application has been preferred seeking extension of time by one week for depositing enhanced amount as directed by order dated 16th April, 2024.

2.

Learned Counsel appearing for the Applicant submits that due to lack of fund GMIDC, Aurangabad was not able to make arrangement for decretal amount within time and therefore there was delay in depositing the same in terms of order dated 16th April, 2024. 3.

In light of the explanation tendered the time to deposit enhanced amount is extended by period of one week from today. 4.

Interim/ad-interim relief granted earlier, if any, to continue till the next date.

Shubham Talle 1 of

13-IA-7426-2025.doc 5.

In event, the amount is not deposited within a period of one week the stay which was granted will stand vacated. 6.

Stand over to 28th April, 2025.