Gayatri Shimpi 56-IA-8671-2025.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE SIDE JURISDICTION INTERIM APPLICATION NO. 8671 OF 2025 WITH INTERIM APPLICATION NO. 8672 OF 2025 IN FIRST APPEAL (ST) NO. 3389 OF 2025 The Executive Engineer Doodhganga Patbhandare Prakalp ....Applicant

Versus

Janardan Ramchandra Mahadeshwar And Ors.

....Respondents ----- Mr. Sachin Gite, Advocate for the Applicant.

Mr. A. R. Patil, AGP for Respondent-State.

----- CORAM : SHIVKUMAR DIGE, J.

DATE : 17th JUNE, 2025.

P.C. :

1.

Heard learned counsel for the Applicant.

2.

Considering the submission of learned counsel for the Applicant and the reasons mentioned in the Application, the impugned order is stayed till the next date, subject to deposit of entire award amount along with accrued interest thereon within 1/2

Gayatri Shimpi 56-IA-8671-2025.doc eight weeks before the Tribunal.

3.

Issue notice to the Respondents, returnable on 12th August, 2025.

(SHIVKUMAR DIGE, J.) by GAYATRI RAJENDRA SHIMPI Date:

2025.06.21 10:31:42 +0530 GAYATRI RAJENDRA SHIMPI 2/2