IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO.175 OF 2025 Pranav Constructions Limited ....Petitioner

Versus

Priyadarshini Co-operative Housing Society Limited

...Respondent

Mr. Prathamesh N. Kamat a/w. Harsh L. Behany a/w. Prachi Sanghvi i/b. HN Legal, Advocates for Petitioner. Mr. Jamshed Ansari, Advocate for Respondent Nos.3 and 4. CORAM: SOMASEKHAR SUNDARESAN, J.

DATE : MAY 6, 2025 PC :

1.

Having briefly heard the parties and taking into account the fact that the IOD has been received on March 27, 2025, it won't be inappropriate to stand over the matter beyond vacation. Let a reply, if any, that any Respondent is desirous of filing, be filed no later than May 30, 2025. Rejoinder, in any, to be filed no later than June 6, 2025. 2.

List on June 12, 2025. On that date, the matter will be dealt with one way or the other.

3.

All actions required to be taken pursuant to this order, shall be taken upon receipt of a downloaded copy as available on this Court's website.

by AARTI GAJANAN PALKAR Date:

2025.05.07 17:37:47 +0530 AARTI GAJANAN PALKAR [ SOMASEKHAR SUNDARESAN, J.] MAY 6, 2025 Aarti Palkar