IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION PETITION NO.659 OF 2025 Puranik Builders Limited ....Petitioner

Versus

Haware Engineers and Builders Private Limited ...Respondent Petitioner was represented, but the appearance has not been given.

Mr. Vagish Mishra i/b. Law Counsellors, Advocate for Respondent.

CORAM: SOMASEKHAR SUNDARESAN, J.

DATE : AUGUST 7, 2025 ORDER :

1.

This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Learned Arbitral Tribunal, which expired on March 17, 2022. 2.

Today, when the matter is called out, Learned Counsel for the parties jointly request for an extension of mandate by a period of six months, bearing in mind the stage at which the arbitral proceedings are placed.

AUGUST 7, 2025 Aarti Palkar

4.CARBP.659.2025.doc 3.

In these circumstances, taking into account the stage at which the arbitral proceedings are placed, this Petition is finally disposed of extending the mandate of the Learned Arbitral Tribunal until December 31, 2025.

4.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] AUGUST 7, 2025 Aarti Palkar