Bombay High CourtCARBP/855/2025disposed off

The President Of India Through Chief Engineer (Construction )/Cpm/Ngp Central Railway v. Kec International Ltd

2025-11-21Hon'Ble Justice Sharmila U. Deshmukh2 pages

2_CARBP855_25.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION COMMERCIAL ARBITRATION PETITION NO.855 OF 2025 The President of India through Chief Engineer (Construction) / CPM / NGP Central Railway ...

Petitioner Vs.

KEC International Limited ...

Respondent WITH INTERIM APPLICATION (L) NO.31606 OF 2025 WITH INTERIM APPLICATION (L) NO.25856 OF 2025 IN COMMERCIAL ARBITRATION PETITION NO.855 OF 2025 --- Mr. Narayan R. Bubna for Petitioner.

Mr. Mustafa Doctor, Senior Advocate a/w. Mr. Anuj Athalye, Mr. Nitin Jain, Mr.Rohan Gupta i/b. Legasis Partners for Respondent. CORAM : MANISH PITALE, J.

DATE : NOVEMBER 21, 2025 P.C. :

.

At the outset, Mr. Bubna, learned counsel for the petitioner submits that permission may be granted to delete the words 'the President of India through' wherever they have been used in this petition.

2.

Permission is granted. The amendment be carried out within two weeks from today.

3.

Heard learned counsel for the petitioner.

4.

It is submitted that by the impugned arbitral interim award, the tribunal has effectively re-written the contract itself, which cannot be 1/2

2_CARBP855_25.doc permitted and that, this is a good ground for interference under Section 34 of the Arbitration and Conciliation Act, 1996. 5.

Issue notice, returnable on 08.01.2026.

6.

It is made clear that this Court may consider finally disposing of the petition on the returnable date. In the meanwhile, within four weeks from today, reply affidavit be filed. Rejoinder affidavit, if any, be filed within a week thereafter.

7.

Liberty to mention in case of urgency.

(MANISH PITALE, J.) Minal Parab 2/2