IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION PETITION NO.1070 OF 2025 Generic Engineering Construction and Projects Ltd

...Petitioner

Versus

Maharashtra Maritime Board

...Respondent

Mr.Rohaan Cama a/w Chetan Shah, Khushboo Rupani, Sharan Shetty and Faranaaz Karbhari i/by HSA Advocate, for the Petitioners.

Mr. Ishwar Nankani a/w Harshvardhan Nankani, Huzefa Khokhawala, karan Parmar and Kartik Gupta i/by Nankani & Associates, for the Respondent.

CORAM

DR. NEELA GOKHALE, J.

DATED:

4TH DECEMBER 2025 PC:- 1.

Mr. Caama, learned counsel for the Petitioner, has tendered a copy of draft amendment. The same is taken on record. Leave to amend Arbitration Petition in terms of draft amendment is granted. Amendment be carried out within a period of three days from today. Reverification stands dispensed with.

4th December 2025

Prasad Rajput (P.A.) 901_CARBP_1070_2025.doc 2.

Mr. Nankani, learned counsel for the Respondent, is at liberty to file Affidavit-in-Reply to the amended Petition which is to be served on him within a day of carrying out amendment. Affidavit-in-Reply be filed within a period of three days thereafter, if so desired, with an advance copy of the same served on the leaned counsel for the Petitioner. 3.

Mr. Caama states that he has already served a copy of the rejoinder to the Respondent. The said Rejoinder be filed in the Registry by tomorrow.

4.

Stand over to 12th December, 2025.