Oshiwara Shree Sai Co-Operative Housing v. The State Of Mahrashtra Through The Principal Secretary
6-IA-876-2025.doc Digitally signed by RUPALI RAJESH WAKODIKAR Date:
2025.07.28 16:03:33 +0530 RUPALI RAJESH WAKODIKAR
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 876 OF 2025 IN WRIT PETITION(ST) NO. 25825 OF 2021 Oshiwara Shree Sai Co-operative Housing ...Applicant
Versus
The State Of Maharashtra Through The Principal Secretary
...Respondent
Ms. Shruti Tulpule a/w Ms. Shivani Samel for the Applicant. Mr. S.B.Gore, A.G.P for the Respondent Nos.1 and 2. Mr. P.G.Lad for the Respondent No.3.
Mr. S.S.Bedekar for the Respondent No.5.
Mr. Nilesh Pandit i/b A.N.Advocate LLP for the Respondent No.7. CORAM : REVATI MOHITE DERE & DR. NEELA GOKHALE, JJ.
DATE : 25 th JULY, 2025 P.C. :
1.
By this interim application, the applicant seeks restoration of the aforesaid writ petition which was dismissed for non-removal of Wakodikar 1/2
6-IA-876-2025.doc the office objections; for extension of time to remove the office objection and for condonation of delay in filing the aforesaid interim application.
2.
It appears that the aforesaid petition was dismissed for non-removal of the office objections vide order dated 2nd June, 2023. Learned Counsel appearing for the contesting respondent Nos.3 and 4 have no objection for restoration of the aforesaid petition. 3.
Even otherwise, for the reasons set out in the application, application is allowed and the aforesaid petition is restored back to its original file. Office objections to be removed within one week from today.
4.
Delay in filing the aforesaid interim application is hereby condoned.
5.
Interim application stands disposed of accordingly. DR. NEELA GOKHALE, J.
REVATI MOHITE DERE, J.
Wakodikar 2/2