IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 1380 OF 2025 IN WRIT PETITION (L) NO. 34722 OF 2024 Monarch Surveyors and Engineering Consultants Limited ... Applicant/Petitioner V/s.

Union of India through the General Manager and Ors.

... Respondents _______________________________________ Ms. Shilpi Jain with Ms. Rashi Shah i/b. M/s. Kartikeya and Associates for the Applicant/Petitioner Mr. N.R. Bubna for Respondent Nos. 1 and 2 Ms. Nisha Kaba with Ms. Mallika Kerketta for Respondent No.3 _______________________________________ CORAM : ALOK ARADHE, CJ. AND M.S. KARNIK, J.

DATE : 21st APRIL 2025 P.C. :

1.

Heard on Interim Application No. 1380 of 2025. The leaned Counsel for the Petitioner is permitted to file an affidavit in rejoinder within a period of three weeks. Let the Writ Petition be listed for hearing on 13th June 2025.

2.

Accordingly, the Interim Application No. 1380 of 2025 is disposed of.

( M.S. KARNIK, J. ) ( CHIEF JUSTICE ) 1/1