← Library
Bombay High CourtIA/2122/2025disposed off

Ajmera Realty And Infra India Limited v. Nikhil Dharamdas Shah

2025-07-03Hon'Ble Shri Justice Somasekhar Sundaresan2 pages

5-ial-13435-2025.doc jsn

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION INTERIM APPLICATION (L) NO.13435 OF 2025 IN COM SUIT (L) NO.13239 OF 2025 Ajmera Realty & Infra India Ltd.

...Applicant / Plaintiff

Versus

Nikhil Dharamdas Shah and Ors.

...Defendants ---------- Mr. Karl Tamboly, Mr. Shrey Shah and Mr. Bhupen Garud i/b. Vidhii Partners for the Applicant / Plaintiff.

Ms. Ankita Singhania, with Ms. Riya Thakkar i/b. Tushar Goradia for the Defendant No.1.

Mr. Aditya Mehta, i/b. Ms. Ravleen Sabharwal for Defendant No.3. ---------- CORAM : R.I. CHAGLA J.

DATE : 3RD JULY, 2025.

ORDER :

1.

Ms. Ankita Singhania, the learned Counsel appearing for the Defendant No.1 states that complete inspection has not been given by the Applicant / Plaintiff. Accordingly, the Affidavit in Reply which was directed to be filed within a period of six weeks from the 1/2

5-ial-13435-2025.doc Order dated 6th May, 2025 has not yet been filed. 2.

Accordingly, the Applicant / Plaintiff shall give inspection of remaining documents to the Defendant by 4th July, 2025. The Defendant No.1 shall file their Affidavit in Reply on or before 11th July, 2025.

3.

The statement made by learned Counsel for the Defendant No.1 recorded in paragraph 1 of the Order dated 6th May, 2025 shall continue to operate till the next date. 4.

Interim Application shall be placed for ad-interim relief on 14th July, 2025.

[ R.I. CHAGLA J. ] 2/2