Bombay High CourtIA/2678/2025disposed off

Deepak Namchand Shah v. Marvelous Builders Pvt Ltd

2025-08-26Hon'Ble Shri Justice Abhay Ahuja2 pages

49-S-684-2013.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION by KANCHAN PRASHANT DHURI Date:

2025.08.26 19:14:33 +0530 KANCHAN PRASHANT DHURI SUIT NO. 684 OF 2013 Deepak Shah ... Plaintiff

Versus

Marvelous Builders Pvt Ltd and others ... Defendants WITH INTERIM APPLICATION NO. 2678 OF 2025 IN SUIT NO. 684 OF 2013 ............

Mr. E.A. Sasi alongwith Mr. Tejas Shinde, Advocate for the Plaintiff. Mr. Aseem Naphade alongwith Mr. Shubham Shah instructed by Mr. Tushar Goradia for the Defendants No.1, 8 and 9A. Mr. Deepak Shah, Plaintiff present.

............

CORAM

:

ABHAY AHUJA, J.

DATE :

26 AUGUST 2025 P.C. :

Suit No. 638 of 2013 :

1.

Once again time is being sought on behalf of the Defendants to file evidence as required in paragraph 2 of the order dated 15 th July 2025.

2.

Let the said evidence positively be filed within a period of four weeks.

Kanchan Dhuri 1/2

49-S-684-2013.doc 3.

Discovery and inspection is to be completed within a period of two weeks thereafter.

4.

The Plaintiff to file statement of admission and denial within a period of two weeks thereafter, with copy to the other side. 5.

List for marking of Plaintiff's documents on 11th November 2025.

6.

Let the Defendant's witness remain present in Court on the next date.

7.

It is made clear that any further request for time will be met with exemplary costs.

Interim Application No. 2678 of 2025 :

8.

No reply has been filed and again time is being sought on behalf of the Defendants to file reply.

9.

Let reply be filed on behalf of the Defendants within a period of two weeks, with copy to the other side. Rejoinder be filed in two weeks thereafter with copy to the other side. 10.

List on 11th November 2025.

11.

It is made clear that any further request for time will be met with exemplary costs.

(ABHAY AHUJA, J.) Kanchan Dhuri 2/2