Steel Manufacturers Association Of Maharashtra v. Vidarbha Industries Association (Via)
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION WRIT PETITION (L) NO. 19437 OF 2025 O2 Renewable Energy VII Pvt Ltd .. Petitioner WRIT PETITION (L)NO.19450 OF 2025 National Solar Energy Federation of India & Ors INTERIM APPLICATION (L) NO.22460 OF 2025 IN WRIT PETITION (L)NO.19450 OF 2025 Tata Power Renewable Energy Ltd ..Applicant .. Respondent WRIT PETITION (L)NO.19529 OF 2025 Distributed Solar Power Association & Ors
WRIT PETITION (L)NO.19640 OF 2025 Sunsure Solapark OD Two Pvt Ltd ..Petitioner WRIT PETITION (L)NO.20635 OF 2025 Alloy Steel Producers Association of India & Ors Maharashtra Electricity Regulatory Commission & Anr .. Respondents WRIT PETITION (L)NO.20790 OF 2025 Green Energy Association, Mumbai ..Petitioner .. Respondent WRIT PETITION (L)NO.20792 OF 2025 Borosil Scientific Ltd ..Petitioner
WRIT PETITION (L)NO.20945 OF 2025 CtrlS Datacentres Ltd ..Petitioner WRIT PETITION (L)NO.21021 OF 2025 Ultratech Cement Ltd & Anr WRIT PETITION (L)NO.21151 OF 2025 NTT Global Data Centres and Cloud Infrastructure India Pvt Ltd & Anr WRIT PETITION (L)NO.21326 OF 2025 Vidarbha Industries Association (VIA) & Ors
INTERIM APPLICATION NO.4092 OF 2025 IN WRIT PETITION (L)NO.21326 OF 2025 Steel Manufacturers Association of Maharashtra ..Applicant/Intervener In the matter between Vidarbha Industries Association (VIA) & Ors Maharashtra Electricity Regulatory Commission & Anr INTERIM APPLICATION (L) NO.22613 OF 2025 IN WRIT PETITION (L)NO.21326 OF 2025 Chamber of Marathwada Industries and Agriculture ..Applicant/Intervener
IN THE MATTER BETWEEN
Vidarbha Industries Association (VIA) & Ors Maharashtra Electricity Regulatory Commission & Anr WRIT PETITION (L)NO.21714 OF 2025 Ampyr Renewable Energy Resoures Twelve A Pvt Ltd & Anr
Mr.Zal Andhyarujina, Senior Advocate a/w Shruti Sardesai, Shrey Shah, Shreya Mukherjee, Sai Archit i/b Hudda and Associates, Advocates for the Petitioner. Mr.Ratnakar Singh, Advocate for Respondent No.1. Mr.Vishal Binod (through V.C.) a/w Sagnik Maitra i/b Cyril Amarchand Mangaldas, Advocates for Respondent No.2.
CORAM
: B. P. COLABAWALLA & FIRDOSH P. POONIWALLA, JJ.
DATE : AUGUST 08, 2025 P. C.
1.
Mentioned. Not on board.
2.
The above matter has been moved because on 6th August 2025 we had finally heard all the above Writ Petitions and reserved the judgment. However in the said order passed on 6th August 2025 we inadvertently forgot to include the continuation of the ad-interim order passed on 1st July 2025 and which was continued from time to time. 3.
Accordingly we clarify that till the judgment is pronounced, the ad-interim order dated 1st July 2025 shall continue.
4.
Personal Assistant of this Court. All concerned will act on production by [FIRDOSH P. POONIWALLA, J.] [B. P. COLABAWALLA, J.]