Activitas Management Advisors Pvt Ltd v. Mind Plus Healthcare Pvt Ltd
1/1 40-IA6217-25.DOC
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO. 6217 OF 2025 IN ARBITRATION APPLICATION NO. 203 OF 2024 Activitas Management Advisors Pvt. Ltd.
... Applicant In the matter of :- Activitas Management Advisors Pvt. Ltd.
... Petitioner
Versus
Mind Plus Healthcare Pvt. Ltd.
... Respondent _______ Mr. Rahul Gupta i/by Yash Jariwala for the Applicant. _______
CORAM
:
ARIF S. DOCTOR, J.
th FEBRUARY, 2026 DATE :
P.C.
1.
This interim application seeks condonation of delay for a period of 53 th July, 2025 by which the captioned days, as well as recall of an order dated 4 Arbitration Petition (which is filed under provision of Section 11 of the Arbitration and Conciliation Act, 1996) came to be dismissed. 2.
Having heard learned Counsel, who has taken me through this Interim Application. Given that I am satisfied that sufficient cause has been shown, in my view, the substantive interest of justice could thereby be served. This Interim Application is allowed, and the Petition under Section 11 of the Act is restored to file. Therefore, this application is accordingly allowed in terms of prayer clause A & B.
[ARIF S. DOCTOR, J.] MPBalekar