IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION INTERIM APPLICATION NO. 6734 OF 2025 IN COMMERCIAL SUIT NO. 84 OF 2024 Prashanth Projects Ltd.

...Plaintiff

Versus

Indian Oil Corporation Ltd.

...Respondent

Mr. Akshay R. Kapadia, for the Plaintiff.

CORAM:

SOMASEKHAR SUNDARESAN, J.

DATE:

June 10, 2026 ORDER :

1.

Mentioned by way of a praecipe for speaking to minutes of the order. Essentially, the submission is that the order needs to be clarified to indicate that re-verification of the amendments allowed earlier is to be dispensed with. 2.

Considering the nature of the amendments, reverification cannot be dispensed with. Time to carry out the amendments is extended by a further period of three weeks from today. Any further request to be made before the Roster Bench.

June 10, 2026 Rutuja Borse

P1-IA-6734-2025.doc 3.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website. [ SOMASEKHAR SUNDARESAN, J.] June 10, 2026 Rutuja Borse