IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO.7543 OF 2025 IN COMMERCIAL ARBITRATION PETITION NO.15 OF 2015 Maharashtra State Power Generation Co. Ltd.

....Applicant

IN THE MATTER BETWEEN

Maharashtra State Power Generation Co. Ltd.

....Petitioner

Versus

M/s Mahalakshmi Infraprojects Ltd.

....Respondent Mr. G.E. Moharir (Through VC) a/w. Mr. A.A. Alaspurkar, for Applicant.

Mr. Mandar Soman, for Respondent.

CORAM: SOMASEKHAR SUNDARESAN, J.

DATE : DECEMBER 03, 2025 ORDER :

1.

Since a challenge under Section 37 of the Arbitration and Conciliation Act, 1996 has already been filed. It would only be appropriate for the Applicant to seek an urgent relief before the Section 37 Court.

2.

The Interim Application is therefore finally disposed of without any orders.

by AARTI GAJANAN PALKAR Date:

2025.12.03 15:03:27 +0530 AARTI GAJANAN PALKAR DECEMBER 03, 2025 Aarti Palkar

903.IA.7543.2025.doc 3.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] DECEMBER 03, 2025 Aarti Palkar