← Library
Bombay High CourtIA/8139/2025disposed off

Shilpi Constructions Engineers And Contractors v. Dipali Balakrishna Goenka

2026-01-06Hon'Ble Shri Justice Somasekhar Sundaresan2 pages

12.IA.8139.2025.doc

IN THE HIGH COURT OF JUDICATURE AT BOMBAY

ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO.8139 OF 2025 IN ARBITRATION PETITION (L) NO.30051 OF 2022 Shilpi Constructions Engineers & Contractors ....Applicant

Versus

Dipali Balakrishna Goenka ....Respondents Mr. Nikhil Mehta i/b. KHC Legal Venture, for Applicant. Mr. C. Keswani a/w. Mr. Harsh Thadani i/b. Economic Laws Practice, for Respondents.

CORAM: SOMASEKHAR SUNDARESAN, J.

DATE : JANUARY 6, 2026 ORDER :

1.

The captioned Petition came to be dismissed by an office order for non-removal of the office objections within the stipulated time period.

2.

Learned Advocate for the Applicant seeks two weeks' time to remove all office objections.

3.

The Learned Advocate for the Applicant shall remove all office objections within a period of two weeks from the date of upload of this order on the website of this Court.

Digitally signed by AARTI GAJANAN PALKAR Date:

2026.01.07 14:30:01 +0530 AARTI GAJANAN PALKAR JANUARY 6, 2026 Aarti Palkar

12.IA.8139.2025.doc 4.

The captioned matter is restored on the docket of this Court. Once the office objections are removed and captioned matter is numbered, the Registry is directed to auto-list the matter as per the Standard Operating Procedure of this Court.

5.

Interim Application filed by the Applicant seeking restoration is finally disposed of.

6.

All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website.

[ SOMASEKHAR SUNDARESAN, J.] JANUARY 6, 2026 Aarti Palkar