United India Insurance Co. Ltd. Through Its Brach Manager v. Vidya Sanjay Chaudhari And Others
931 CA NO. 3047 OF 2026.odt
IN THE HIGH COURT OF JUDICATURE OF BOMBAY
BENCH AT AURANGABAD 931 CIVIL APPLICATION NO. 3047 OF 2026 IN FAST/6812/2026 United India Insurance Co. Ltd. Through Its Brach Manager
VERSUS
Vidya Sanjay Chaudhari And Others ...
Mr. Deshmukh Mohit Rameshrao, Advocate for Applicant WITH CIVIL APPLICATION NO. 3048 OF 2026 IN FAST/6812/2026 CORAM : SANJAY A. DESHMUKH, J.
DATE : 13.03.2026 PER COURT :- APPLICATION FOR DELAY 1.
Heard.
2.
This is an application for condonation of delay of 52 days caused in filing the first appeal.
3.
Perused the application. For the reasons stated therein, the application deserves to be allowed in the interest of justice as the delay is neither deliberate nor intentional. Hence the following order:
::ORDER::
a.
Civil Application is allowed.
b.
The delay of 52 days caused in filing the first appeal is condoned.
(( 2 )) 931 CA NO. 3047 OF 2026 FIRST APPEAL .
Issue notice to the respondents, returnable on 03.07.2026.
APPLICATION FOR STAY 1.
This is an application seeking stay to the execution and operation of the impugned judgment and award. 2.
Issue notice to the respondents, returnable on 03.07.2026. 3.
Till then, there shall be ad-interim-stay to the execution and operation of the impugned judgment and award on condition that appellant shall deposit the entire amount under impugned judgment and award with the Registry of this Court within twelve weeks from today.
4.
If the award amount is not deposited within the stipulated period, ad-interim-stay granted by this Court shall be vacated without further reference to this Court.
[ SANJAY A. DESHMUKH, J. ] HRJadhav