Executive Engineer Medium Project Division Dharashiv v. Kerba Bapu Kharat Therough Lrs
2026:BHC-AUG:14289
IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH
AT AURANGABAD 96 CIVIL APPLICATION NO. 3761 OF 2026 IN FAST/36529/2025 EXECUTIVE ENGINEER MEDIUM PROJECT DIVISION DHARASHIV
VERSUS
KERBA BAPU KHARAT THEROUGH LRS ...
Advocate for Applicant : Mr. Avishkar Sukhdeo Shelke. AGP for Respondent/s-State : Mr. C. V. Bhadane. ...
CORAM :
SHAILESH P. BRAHME, J.
DATE :
02.04.2026 PER COURT :- 1.
Applicant seeks to condone delay of 41 days in restoration of the first appeal which was disposed of due to non-removal of office objections.
2.
For the reasons stated in the application, delay stands condoned. First appeal stands restored to its original position. Civil application is allowed.
3.
Applicant shall remove office objections within a period of four (4) weeks from today.
(SHAILESH P. BRAHME, J.) ...
vmk/-