Bajaj Alianz General Insurance Com. Ltd. Through Its Branch Manager v. Sunil Kalyanmal Bharuka And ORS.
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
BENCH AT AURANGABAD 36 CIVIL APPLICATION NO. 4973 OF 2026 IN FAST/10696/2026 WITH CIVIL APPLICATION NO. 4974 OF 2026 IN FAST/10696/2026 BAJAJ ALIANZ GENERAL INSURANCE COM. LTD. THROUGH ITS BRANCH MANAGER
VERSUS
SUNIL KALYANMAL BHARUKA AND ORS.
..
Mr. M. R. Deshmukh, Advocate for the applicant CORAM : SANJAY A. DESHMUKH, J.
DATED : 27th APRIL, 2026 P. C. :- ORDER BELOW CIVIL APPLICATION NO. 4973 OF 2026 1.
The present Civil Application is filed for condonation of delay of 45 days caused in filing the first appeal.
2.
Perused the application and heard learned advocate for the applicant.
3.
Considering the reasons stated in the application, it appears that the delay caused is not deliberate. Therefore, the application is allowed. The delay in filing the appeal is condoned in the interest of justice. 4.
In FA(ST) No. 10696 of 2026, issue notice to the Respondents, 36 CA 4973.2026.odt
returnable on 6th July, 2026.
ORDER BELOW CIVIL APPLICATION NO. 4974 OF 2026 5.
This is an application for seeking granting stay to the execution, operation and implementation of impugned judgment and award. 6.
Perused the application. Heard learned advocate for the applicant. Considering the peculiar facts of the case and the grounds stated in the application, stay is granted subject to deposit entire amount of compensation under award along with interest accrued and costs, within 12 weeks from today. With this condition, application is allowed and disposed of accordingly.
7.
It is clarified that if the amount, as directed above, is not deposited within the aforesaid period, the stay granted by this Court shall stand vacated without further reference to the Court. (SANJAY A. DESHMUKH, J.) ssp 36 CA 4973.2026.odt