Elanit G Jacobs v. Relliance Construction Co
P11.CP.98.2026.doc HARSHADA H. SAWANT (P.A.) IN IN THE THE HIGH HIGH COURT COURT OF OF JUDICATURE JUDICATURE AT AT BOMBAY BOMBAY CIVIL APPELLATE JURISDICTION CIVIL APPELLATE JURISDICTION CONTEMPT PETITION NO.98 OF 2026 Elanit G. Jacobs .. Petitioner
Versus
M/s. Relliance Construction Co. and Anr.
.. Respondents ....................
Ms. Trupti Gosavi, Advocate for Petitioner.
Mr. Makarand Raut, Advocate for Respondent No.1. ...................
CORAM
: MILIND N. JADHAV, J.
DATE : MARCH 04, 2026 P.C.
:
1.
Not on Board. Mentioned by way of filing praecipe dated 04.03.2026. Perused the praecipe filed for Speaking to the Minutes of order dated 26.02.2026.
2.
Heard Mr. Gosavi, learned Advocate for Petitioner and Mr. Raut, learned Advocate for Respondent No.1.
3.
In fourth line of paragraph No.3 on page No.1 and fifth line of paragraph No.4 of the order dated 26.02.2026, the interest rate recorded as '10.70%' be corrected as '10.75%'. 4.
Necessary corrections be carried out in the original order and fresh copy be uploaded.
5.
Praecipe is disposed.
H. H. SAWANT [ MILIND N. JADHAV, J. ] by HARSHADA HANUMANT SAWANT Date: