Ir Civil Engineers And Contractors Pvt Ltd v. Ng Suncity Phase Iii Coop Hsg Soc Ltd
Renuka P2-ARBPL-675-2026
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION COMMERCIAL ARBITRATION PETITION NO. 675 OF 2026 M/s. IR Civil Engineers and Contractors Pvt. Ltd.
...Petitioner
V/s.
M/s. N. G. Suncity Phase III Co-op Hsg.
Soc. Ltd.
...Respondent
________________ Mr. Niranjan Kandade i/b Nandu Pawar for the Petitioner. ________________ CORAM: SANDEEP V. MARNE, J.
DATED: 12 MARCH 2026.
P.C.:
1) Not on board. Upon being mentioned, taken on board. 2) Motion is made for speaking to the minutes of order dated 10 February 2026.
3) In paragraph 2, in line no. 9 the date '30 October 2020' be substituted by the date '30 October 2025'.
4) The order dated 10 February 2026 be corrected accordingly. [SANDEEP V. MARNE, J.] Page No.