Relcon Infraprojects Limited v. Tripti Cooperative Housing Society Limited
2-ARBP-154-2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION ARBITRATION PETITION NO. 154 OF 2026 Relcon Infraprojects Limited
...Petitioner
Versus
Tripti Cooperative Housing Society Limited
...Respondents
Ms. Akansha A. Mishra a/w Ms. Shriya Mehta & Rishu Mishra, for the Petitioner.
Mr. Rahul Arora a/w Anita Adsul, for the Respondent No. 2-5, 8-10 & 12-15.
CORAM
: SOMASEKHAR SUNDARESAN, J.
DATE : APRIL 30 , 2026 ORDER :
1.
This is a Petition under Section 29-A of the Arbitration and Conciliation Act, 1996, seeking an extension of mandate of the Arbitral Tribunal, which expired on March 16, 2026.
2.
Today, when the matter is called out, Learned Counsel for the parties jointly request for an extension of mandate by a period of nine months, bearing in mind the stage at which the arbitral proceedings are placed. 3.
In these circumstances, taking into account the stage at which the Arbitral proceedings are placed, this Petition is finally disposed of extending APRIL 30, 2026 Rutuja Borse
2-ARBP-154-2026.doc the mandate of the Arbitral Tribunal for a period of nine months, i.e. rounded up to January 31, 2027.
4.
All actions required to be taken pursuant to this order shall be taken upon receipt of a downloaded copy as available on this Court's website. [ SOMASEKHAR SUNDARESAN, J.] APRIL 30, 2026 Rutuja Borse