M/S Digvijay Construction Corpn v. Union Of India
53-ia-1151-2026.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION INTERIM APPLICATION NO.1151 OF 2026 IN COMM. EXECUTION APPLICATION NO.17 OF 2026 M/s. Digvijay Construction Corpn.
..
Applicant/ Appellant.
v/s.
Union of India ..
Respondent.
Ms. Rachana Harpale i/b. Prithvi Aringale, for the Applicant. Ms. Leena Patil, for the Respondent.
by SMITA RAJNIKANT JOSHI Date:
2026.04.09 17:32:44 +0530 SMITA RAJNIKANT JOSHI CORAM: FIRDOSH P. POONIWALLA,J.
DATE : 9th APRIL, 2026.
P. C:- 1.
This Interim Application has been filed for recalling the Order dated 3rd December, 2025 pertaining to the Applicant's Application and to restore Commercial Execution Application No. 17 of 2026. I have heard the learned Counsel for the parties. In my view, sufficient cause has been shown in the Interim Application for restoring the Commercial Execution Application No. 17 of 2026. In these circumstances, the Interim Application is allowed in terms of prayer clause (a) which reads as under:- S.R.JOSHI
53-ia-1151-2026.doc "(a):- This this Hon'ble Court may recall the Order dated December 3, 2025 pertaining to the Applicant's Application and restore the Commercial Execution Application No. 17 of 2026."
In the facts and circumstances of the case, there will be no order at to costs.
(FIRDOSH P. POONIWALLA,J.) S.R.JOSHI