2026.03.18 13:07:19 +0530 ORDINARY ORIGINAL CIVIL JURISDICTION KANCHAN PRASHANT DHURI INTERIM APPLICATION NO. 1473 OF 2026 IN EXECUTION APPLICATION NO. 85 OF 2008 Sankaranarayana Construction (Blore) Pvt Ltd ... Applicant
Versus
Gammon India Limited ... Respondent ............
Mr. Avinash Joshi, Advocate for the Applicant. Mr. Ramesh Sahu, Advocate for the Respondent. ............
CORAM
:
ABHAY AHUJA, J.
DATE :
17 MARCH 2026 P.C. :
1.
Both the learned Counsel agree that in view of the pendency of the Petition under Section 34 of the Arbitration and Conciliation Act, 1996 in the Madras High Court, this Interim Application can be disposed with a direction to the Prothonotary & Senior Master to keep the sum of Rs.56,07,439/- deposited in this Court, invested in an interest bearing fixed deposit with a Nationalized Bank to be renewed periodically. Ordered accordingly.
Kanchan Dhuri 1/2
58-IA-1473-2026.doc 2.
Copies of the bank guarantees that have been invoked be returned to the Applicant after keeping certified copies of the same on record.
3.
The Interim Application accordingly stands disposed. (ABHAY AHUJA, J.) Kanchan Dhuri 2/2